Keypoint Management System

KEYPOINT MANAGEMENT SYSTEM MAKES OUR PRODUCTION CONTROL PRACTICABLE

In our?keypoint management system, all production procedures are standardized based on enterprise production principles and international standards. And each link has a strict inspection system to ensure all key points regarding the product quality are under controlled. We implement our keyponint management from the following aspects.

MATERIAL ASSURANCE

We check labels for right materials before production. Generally, we follow the following steps.

  1. Check the labeled materials in the warehouse and mill certifications.

  2. Make sure the materials are in compliance with customers' requirements.

Labeled steel coils are placed in the warehouse.
FF5E14


In-Process Production Control

Wire Drawing & Double-Twisted Weaving

Computer-monitored wire drawing ensures exact diameters (2.0mm, 2.2mm, 2.7mm, or custom)

Automated weaving machines produce uniform double-twisted hexagonal mesh

Twist length and tightness are checked continuously

image.png

Mesh Opening Tolerance

Mesh OpeningToleranceStandard
60×80mm±5%EN 10223-3
80×100mm±5%EN 10223-3
100×120mm±5%EN 10223-3
Custom sizesAs agreedFactory standard
gabion baskets (77).JPGgabion baskets (76).JPG


Diaphragm & Selvedge Wire

30 mechanical flanging machines?ensure diaphragms are correctly spaced

Selvedge wires are double-twisted to prevent unraveling

Edge reinforcement guarantees the box retains shape after stone filling

03.jpggabion baskets (99).JPG


Coating & Finish Inspection

MaterialCoating ThicknessTest MethodExpected Life
Galvanized wire60–80µm (≥245g/m²)Magnetic gauge, Preece test15–20 years
PVC coated wire0.4–0.6mm over galvanizedMandrel bend, cross-cut adhesion20–25 years
Galfan wire60–80µmSalt spray (ASTM B117)30–40 years
10% Al-Zn alloy wire60–80µmSalt spray, composition analysis40–50+ years


Final Product Testing

TestMethodAcceptance Criteria
Mesh tensile strengthPull test on random samplesMeets EN 10223-3 or ASTM A975
Box assemblyFold and assemble sample boxDiaphragms align, corners connect
Dimensional checkMeasure length, width, heightTolerance ≤ ±5%
Coating integrityVisual + thickness gauge + adhesionNo bare metal, uniform coverage
Salt spray (on request)ASTM B117No corrosion after specified hours
Random samples from each batch are tested. Test reports are kept for traceability.


Material Selection Guide

Project EnvironmentRecommended Material
General soil, normal humidityGalvanized wire
Coastal area, high salt sprayGalfan wire or 10% Al-Zn alloy
Acidic soil, industrial pollution10% Al-Zn alloy or PVC coated
Fresh water (rivers, lakes)Galvanized wire
Marine environmentGalfan + PVC coated
Long-life infrastructure (50+ years)10% Al-Zn alloy